We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Share Merimbula Airport Runway Starter Extension Stage 2 on FacebookShare Merimbula Airport Runway Starter Extension Stage 2 on X (formerly Twitter)Share Merimbula Airport Runway Starter Extension Stage 2 on LinkedinEmail Merimbula Airport Runway Starter Extension Stage 2 link
An additional 80m will be added to the starter extensions at each end of the Merimbula Airport runway.
Project type:
Assets and Technical Services
Budget:
$8.7m
Funded by:
NSW Regional Economic Development and Community Investment Program Commonwealth Government Regional Airports Program Round 4
Project schedule:
In progress
Proposed completion date:
December 2027
Project Overview
Council is delivering Stage 2 of the Merimbula Airport Runway Starter Extension project, with 80m being added to the starter extensions at each end of the Merimbula airport runway.
Purpose
The project will complete the full runway configuration identified in the Merimbula Airport Master Plan 2043.
This will enable a greater range of aircraft to service the airport, particularly passenger airline aircraft which are increasing in size as airlines replace ageing aircraft.
The project also meets the requirement in the Development Approval, which stipulates that the works must be completed by 21 December 2030.
Funding
NSW Regional Economic Development and Community Investment Program - $5m
Commonwealth Government Regional Airports Program Round 4 - $3.778m
Connection to Council's Community Strategic Plan
This project aligns with Bega Valley Shire Council Community Strategic Plan 2040 through part B of the ‘Plan’ – ‘Our Economy’ page 19; Strategy B.5 ‘Our key industries are resilient and strong’.
An additional 80m will be added to the starter extensions at each end of the Merimbula Airport runway.
Project type:
Assets and Technical Services
Budget:
$8.7m
Funded by:
NSW Regional Economic Development and Community Investment Program Commonwealth Government Regional Airports Program Round 4
Project schedule:
In progress
Proposed completion date:
December 2027
Project Overview
Council is delivering Stage 2 of the Merimbula Airport Runway Starter Extension project, with 80m being added to the starter extensions at each end of the Merimbula airport runway.
Purpose
The project will complete the full runway configuration identified in the Merimbula Airport Master Plan 2043.
This will enable a greater range of aircraft to service the airport, particularly passenger airline aircraft which are increasing in size as airlines replace ageing aircraft.
The project also meets the requirement in the Development Approval, which stipulates that the works must be completed by 21 December 2030.
Funding
NSW Regional Economic Development and Community Investment Program - $5m
Commonwealth Government Regional Airports Program Round 4 - $3.778m
Connection to Council's Community Strategic Plan
This project aligns with Bega Valley Shire Council Community Strategic Plan 2040 through part B of the ‘Plan’ – ‘Our Economy’ page 19; Strategy B.5 ‘Our key industries are resilient and strong’.